2025 Concrete and Asphalt Work 

Concrete work is scheduled to begin on Monday, July 14th. Please see the phasing map below. 

 

Resident requests for swale/gutter replacements are not included on this map, they will be provided on a specific map that will be shared later this week. 

 

Tentative Concrete & Asphalt Schedule: 

Concrete:  7/14 - 7/24 (no weekends)

Mill Asphalt:  8/4

Pave New Asphalt:  8/5 - 8/6

Infrared Asphalt Patching:  8/7 - 8/8

 

We will share asphalt phasing maps shortly, please check the Metro website for updates. 

 

Concrete Phasing: 

Aerial map with work phases 1 (7/14-7/16), 2 (7/16-7/17), 3 (7/17-7/24), car removal instructions, and irrigation note.

To enlarge the map, please select the following link: 

Concrete Phasing Map (Rough Durations) (PDF)

 